Status: On time, to budget

A tidy little air conditioning and ventilation project that involved a fair bit of sub-contractor co-ordination.

Points to Note

The builder and our subbies were a big help on this job. Part of our scope was the supply and project management of the science lab fume cupboard and the under floor heating systems. Throw in pipe welders and it certainly made for a very rapid learning curve. Another interesting challenge involved supplying the exposed stainless steel supply air duct work – what a work of art!