Key Projects
Fliway
| Location: | Westney Rd, Mangere |
| Value: | $340,000 |
| Commencment: | June 2007 |
| Completion: | October 2007 |
| Status: | On time, to budget |
A large office/warehouse complex comprising of Temperzone ducted split systems and warehouse ventilation
Points to Note
A straight forward build to a Pacific Consultants design. Relatively tight program dictated by MacQuarie Goodman (the client) who also demanded a high standard of workmanship. A note must be mentioned of our controls sub-contractor who design/built the digital controls system within a very tight timeframe & delivered when it mattered– well done Roy. Meat and two veg for the Chillex team
Key Contacts
Chillex Services
Project Manager: Graham Davis
Phone: (09) 633 4072
Project Manager: Graham Davis
Phone: (09) 633 4072
Macrennie Construction Limited
Site Manager: Tim O’Leary
Phone: (09) 525 3330
Site Manager: Tim O’Leary
Phone: (09) 525 3330